Onshore wind project 401, Baker County

Onshore wind project 401, Baker County is a 10.0 MW onshore wind request built and operating in the West interconnection queue, in Baker County, Oregon, connecting to Idaho Power Company.

Queue statusOperating
  1. PlanningQueued Dec 2012 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
401
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Connection point (POI)
138 kV
Location
Baker County, Oregon
Technology
Wind: 10.0 MW
Total requested
10.0 MW
Service type
Other
Study phase
IA Executed
Queue status
Operational
Entered queue
13 December 2012
Proposed online date
December 2017

Location

Marker shows the centre of Baker County; the queue data does not give exact sites.