United States › Grid › Interconnection queues › Arkansas
SOLAR + STORAGE · MISOSolar + storage project J4088, Lee County
Solar + storage project J4088, Lee County is a 340 MW solar + storage request in interconnection study in the MISO interconnection queue, in Lee County, Arkansas, connecting to ENTERGY ARKANSAS.
Queue statusIn planning
- PlanningQueued Oct 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Mar 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J4088
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY ARKANSAS
- Connection point (POI)
- Wheatley 500 kV Switching Station (being built by J1710 & J1820)
- Location
- Lee County, Arkansas
- Technology
- Solar: 340 MW · Battery
- Total requested
- 340 MW
- Service type
- Network resource (NRIS)
- Queue status
- Active
- Entered queue
- 6 October 2025
- Proposed online date
- March 2028
Location
Marker shows the centre of Lee County; the queue data does not give exact sites.
Other requests in Lee County
- Solar project J552, Lee CountySolar · 100 MW · agreement signed
- Solar project J2088, Lee CountySolar · 400 MW · in study
- Solar project J1710, Lee CountySolar · 300 MW · in study
- Solar project J2237, Lee CountySolar · 185 MW · in study
- Onshore wind project J2437, Lee CountyOnshore wind · 175 MW · in study
- Solar project J1820, Lee CountySolar · 100 MW · in study
- Solar + storage project J2649, Lee CountySolar + storage · 250 MW · withdrawn
- Battery storage project J3584, Lee CountyBattery storage · 215 MW · withdrawn
- Solar project J2787, Lee CountySolar · 200 MW · withdrawn
- Solar project J368, Lee CountySolar · 200 MW · withdrawn
- Solar project J380, Lee CountySolar · 199 MW · withdrawn
- Solar project J3579, Lee CountySolar · 135 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem