SOLAR Β· MISO

Solar project J3579, Lee County

Solar project J3579, Lee County is a 135 MW solar request withdrawn in the MISO interconnection queue, in Lee County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3579
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
MARIANNA WEST SS - MARIANNA 115.0kV
Location
Lee County, Arkansas
Technology
Solar: 135 MW
Total requested
135 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
17 April 2024
Proposed online date
December 2028
Withdrawn
December 2025

Location

Marker shows the centre of Lee County; the queue data does not give exact sites.

Power plants in Arkansas Β· Transmission lines in Arkansas

Other requests in Lee County