SOLAR + STORAGE Β· MISO

Solar + storage project J2649, Lee County

Solar + storage project J2649, Lee County is a 250 MW solar + storage request withdrawn in the MISO interconnection queue, in Lee County, Arkansas, connecting to ENTERGY ARKANSAS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedMar 2023 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2649
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY ARKANSAS
Connection point (POI)
WEST MEMPHIS EHV - KEO EHV 500kv
Location
Lee County, Arkansas
Technology
Solar: 250 MW Β· Battery
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
September 2027
Withdrawn
March 2023

Location

Marker shows the centre of Lee County; the queue data does not give exact sites.