United States › Grid › Interconnection queues › Louisiana
SOLAR · MISOSolar project J1598, Calcasieu Parish County
Solar project J1598, Calcasieu Parish County is a 325 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Calcasieu Parish County, Louisiana, connecting to ENTERGY LOUISIANA.
Queue statusConsented
- PlanningQueued Dec 2023 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1598
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- ENTERGY LOUISIANA
- Connection point (POI)
- Goos Ferry
- Location
- Calcasieu Parish County, Louisiana
- Technology
- Solar: 325 MW
- Total requested
- 325 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA In Process; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 11 December 2023
- Proposed online date
- September 2026
Location
Marker shows the centre of Calcasieu Parish County; the queue data does not give exact sites.
Other requests in Calcasieu Parish County
- Entergy Louisiana LRZ 9 Generation ResourceGas · 770 MW · in study
- Solar + storage project J2899, Calcasieu Parish CountySolar + storage · 250 MW · in study
- Battery storage project J4079, Calcasieu Parish CountyBattery storage · 150 MW · in study
- Solar project J2292, Calcasieu Parish CountySolar · 50.0 MW · in study
- Gas project J484, Calcasieu Parish CountyGas · 1,056 MW · built
- Gas project J3796, Calcasieu Parish CountyGas · 770 MW · withdrawn
- Solar project J2176, Calcasieu Parish CountySolar · 680 MW · withdrawn
- Solar + storage project J2890, Calcasieu Parish CountySolar + storage · 440 MW · withdrawn
- Gas project J331, Calcasieu Parish CountyGas · 338 MW · withdrawn
- Solar project J2163, Calcasieu Parish CountySolar · 200 MW · withdrawn
- Solar project J1541, Calcasieu Parish CountySolar · 200 MW · withdrawn
- Solar project J2167, Calcasieu Parish CountySolar · 198 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem