Gas project J484, Calcasieu Parish County

Gas project J484, Calcasieu Parish County is a 1,056 MW gas request built and operating in the MISO interconnection queue, in Calcasieu Parish County, Louisiana.

Queue statusOperating
  1. PlanningQueued Sep 2015 (completed)
  2. ConsentedJul 2018 (completed)
  3. Construction (completed)
  4. OperatingJul 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J484
Grid region
MISO (Midcontinent)
Connection point (POI)
Existing Entergy Nelson Power Station
Location
Calcasieu Parish County, Louisiana
Technology
Gas: 1,056 MW
Total requested
1,056 MW
Study phase
GIA
Queue status
Operational
Entered queue
14 September 2015
Agreement signed
27 July 2018
Proposed online date
July 2019
Came online
July 2019

Location

Marker shows the centre of Calcasieu Parish County; the queue data does not give exact sites.