United States › Grid › Interconnection queues › Louisiana
GAS · MISOGas project J484, Calcasieu Parish County
Gas project J484, Calcasieu Parish County is a 1,056 MW gas request built and operating in the MISO interconnection queue, in Calcasieu Parish County, Louisiana.
Request details
- Queue ID
- J484
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Existing Entergy Nelson Power Station
- Location
- Calcasieu Parish County, Louisiana
- Technology
- Gas: 1,056 MW
- Total requested
- 1,056 MW
- Study phase
- GIA
- Queue status
- Operational
- Entered queue
- 14 September 2015
- Agreement signed
- 27 July 2018
- Proposed online date
- July 2019
- Came online
- July 2019
Location
Marker shows the centre of Calcasieu Parish County; the queue data does not give exact sites.
Other requests in Calcasieu Parish County
- Solar project J1598, Calcasieu Parish CountySolar · 325 MW · agreement signed
- Entergy Louisiana LRZ 9 Generation ResourceGas · 770 MW · in study
- Solar + storage project J2899, Calcasieu Parish CountySolar + storage · 250 MW · in study
- Battery storage project J4079, Calcasieu Parish CountyBattery storage · 150 MW · in study
- Solar project J2292, Calcasieu Parish CountySolar · 50.0 MW · in study
- Gas project J3796, Calcasieu Parish CountyGas · 770 MW · withdrawn
- Solar project J2176, Calcasieu Parish CountySolar · 680 MW · withdrawn
- Solar + storage project J2890, Calcasieu Parish CountySolar + storage · 440 MW · withdrawn
- Gas project J331, Calcasieu Parish CountyGas · 338 MW · withdrawn
- Solar project J2163, Calcasieu Parish CountySolar · 200 MW · withdrawn
- Solar project J1541, Calcasieu Parish CountySolar · 200 MW · withdrawn
- Solar project J2167, Calcasieu Parish CountySolar · 198 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem