GAS Β· MISO

Gas project J3796, Calcasieu Parish County

Gas project J3796, Calcasieu Parish County is a 770 MW gas request withdrawn in the MISO interconnection queue, in Calcasieu Parish County, Louisiana, connecting to ENTERGY LOUISIANA.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedSep 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3796
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY LOUISIANA
Connection point (POI)
NELSON 230 SWYD
Location
Calcasieu Parish County, Louisiana
Technology
Gas: 770 MW
Total requested
770 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
17 April 2024
Proposed online date
November 2028
Withdrawn
September 2025

Location

Marker shows the centre of Calcasieu Parish County; the queue data does not give exact sites.

Power plants in Louisiana Β· Transmission lines in Louisiana

Other requests in Calcasieu Parish County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem