United States › Grid › Interconnection queues › Idaho
SOLAR + STORAGE · WESTSolar + storage project 655, Bear Lake County
Solar + storage project 655, Bear Lake County is a 325 MW solar + storage request suspended in the West interconnection queue, in Bear Lake County, Idaho, connecting to Idaho Power Company.
Queue statusPaused / redesign
- PlanningQueued May 2022 (current stage)
- ConsentedDec 2023 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 655
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Idaho Power Company
- Developer
- Aurora Solar LLC
- Connection point (POI)
- Bridger–Populus 345kV Line
- Location
- Bear Lake County, Idaho
- Technology
- Solar: 325 MW · Battery
- Total requested
- 325 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA Executed
- Queue status
- Suspended
- Entered queue
- 10 May 2022
- Agreement signed
- 14 December 2023
- Proposed online date
- September 2026
Location
Marker shows the centre of Bear Lake County; the queue data does not give exact sites.
Other requests in Bear Lake County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem