Other project 590, Elmore County

Other project 590, Elmore County is a 330 MW other request with a signed interconnection agreement in the West interconnection queue, in Elmore County, Idaho, connecting to Idaho Power Company.

Queue statusConsented
  1. PlanningQueued Dec 2020 (completed)
  2. ConsentedAug 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
590
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Developer
Appaloosa Wind And Solar LLC
Connection point (POI)
BOBN–MPSN #2 230kV
Location
Elmore County, Idaho
Technology
Solar: 330 MW · Wind · Battery
Total requested
330 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Active
Entered queue
15 December 2020
Agreement signed
1 August 2023
Proposed online date
June 2027

Location

Marker shows the centre of Elmore County; the queue data does not give exact sites.

Power plants in Idaho · Transmission lines in Idaho

Other requests in Elmore County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem