Solar + storage project 604, Elmore County

Solar + storage project 604, Elmore County is a 100 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Elmore County, Idaho, connecting to Idaho Power Company.

Queue statusConsented
  1. PlanningQueued May 2021 (completed)
  2. ConsentedJan 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
604
Grid region
West (non-ISO utilities)
Utility / transmission owner
Idaho Power Company
Developer
Crimson Orchard Solar LLC
Connection point (POI)
Danskin 230kV Substation
Location
Elmore County, Idaho
Technology
Solar: 100 MW · Battery
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Active
Entered queue
27 May 2021
Agreement signed
24 January 2023
Proposed online date
June 2026

Location

Marker shows the centre of Elmore County; the queue data does not give exact sites.

Power plants in Idaho · Transmission lines in Idaho

Other requests in Elmore County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem