Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 28 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Rowdy Creek Solar
Solar + storage · Rowdy Creek Solar LLC
352 MWAgreement signed Lamar, TXERCOT Jan 2022target 2027
Cottonwood Bayou Solar
Solar · Cottonwood Bayou Solar, LLC
351 MWAgreement signed Brazoria, TXERCOT Sep 2017target 2026
Fighting Jays Solar
Solar · AP Solar Holdings, LLC
351 MWAgreement signed Fort Bend, TXERCOT Mar 2019target 2026
Funston Solar
Solar · Funston Solar LLC
351 MWAgreement signed Jones, TXERCOT Feb 2024target 2027
Brookesmith Storage
Battery storage · Brookesmith Storage LLC
351 MWIn study Brown, TXERCOT Apr 2025target 2029
Solar + storage project ERAS-2025-030, Chaves County
Solar + storage
350 MWIn study Chaves, NMSPP Oct 2025target 2030
Solar + storage project Q332, Maricopa County
Solar + storage
350 MWUnder construction Maricopa, AZWest Mar 2020target 2024
Solar + storage project J2390, Fulton County
Solar + storage
350 MWIn study Fulton, ILMISO Sep 2022target 2026
Onshore wind project G0955, Lincoln County
Onshore wind
350 MWIn study Lincoln, WAWest Oct 2023target 2026
Gas project J2944, Portage County
Gas
350 MWIn study Portage, WIMISO Sep 2022target 2027
Onshore wind project GEN-2016-141, Texas County
Onshore wind
350 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Solar + storage project Company NB, White Pine County
Solar + storage
350 MWPaused / redesign White Pine, NVWest Mar 2022target 2030
Solar project Company IF, Humboldt County
Solar
350 MWAgreement signed Humboldt, NVWest Mar 2018target 2026
Battery storage project Company 242, Clark County
Battery storage
350 MWAgreement signed Clark, NVWest Mar 2023target 2028
Onshore wind project J3623, Sunflower County
Onshore wind
350 MWIn study Sunflower, MSMISO Apr 2024target 2028
Onshore wind project J3521, Shelby County
Onshore wind
350 MWIn study Shelby, ILMISO Apr 2024target 2028
Solar + storage project J1946, Jasper County
Solar + storage
350 MWIn study Jasper, MSMISO Aug 2021target 2024
Other project Q606, Maricopa County
Other
350 MWIn study Maricopa, AZWest May 2025target 2030
Solar project AH2-340, Stark County
Solar
350 MWIn study Stark, ILPJM Mar 2022target 2027
Solar project GEN-2024-289, Henry County
Solar
350 MWIn study Henry, MOSPP Mar 2025target 2029
Onshore wind project GI-TC-2024-25, Weld County
Onshore wind
350 MWIn study Weld, COWest May 2024target 2028
Battery storage project Q584, Pinal County
Battery storage
350 MWIn study Pinal, AZWest May 2025target 2029
Battery storage project GEN-2021-005, Saline County
Battery storage
350 MWAgreement signed Saline, KSSPP May 2021target 2030
Onshore wind project GEN-2016-142, Texas County
Onshore wind
350 MWAgreement signed Texas, OKSPP Nov 2016target 2029
Solar + storage project GEN-2024-280, Andrews County
Solar + storage
350 MWIn study Andrews, TXSPP Mar 2025target 2029
Battery storage project AH2-414, Huntington County
Battery storage
350 MWIn study Huntington, INPJM Mar 2022target 2026
Gas project Q519, Maricopa County
Gas
350 MWIn study Maricopa, AZWest Mar 2023target 2028
Battery storage project J3872, Wayne County
Battery storage
350 MWIn study Wayne, MIMISO Jan 2025target 2029
Dateland Energy Complex
Solar + storage
350 MWAgreement signed Yuma, AZCAISO Apr 2020target 2027
Onshore wind project J4203, Huron County
Onshore wind
350 MWIn study Huron, MIMISO Jun 2025target 2028
Battery Storage
Battery storage
350 MWIn study Bristol, MAISO-NE Oct 2023target 2027
Solar project J3889, Union County
Solar
350 MWIn study Union, ARMISO Feb 2025target 2030
Gas project J2945, Washington County
Gas
350 MWIn study Washington, IAMISO Sep 2022target 2027
Onshore wind project G0954, Lincoln County
Onshore wind
350 MWIn study Lincoln, WAWest Oct 2023target 2026
Battery storage project S0026, Converse County
Battery storage
350 MWIn study Converse, WYWest Feb 2024target 2026
Solar project J3209, Rapides Parish County
Solar
350 MWIn study Rapides Parish, LAMISO Sep 2022target 2026
Solar project GEN-2020-084, Burt County
Solar
350 MWAgreement signed Burt, NESPP Apr 2020target 2030
Onshore wind project 21-08242, Laramie County
Onshore wind
350 MWIn study Laramie, WYWest Aug 2021target 2025
Solar + storage project Company OA, Humboldt County
Solar + storage
350 MWPaused / redesign Humboldt, NVWest Sep 2022target 2030
Solar + storage project Company 173, Clark County
Solar + storage
350 MWPaused / redesign Clark, NVWest Nov 2018target 2024
Solar project GEN-2024-338, Johnston County
Solar
350 MWIn study Johnston, OKSPP Mar 2025target 2030
Solar project AG2-436, Sussex County
Solar · Monarch Solar, LLC
350 MWIn study Sussex, VAPJM Apr 2025target 2023
Panther Grove Wind
Onshore wind
350 MWAgreement signed Woodford, ILPJM Sep 2018target 2027
Resilient NY Energy Storage
Battery storage · Resilient NY Storage, LLC by Hanwha Energy USA Holdings Corporation, its Manager
349 MWIn study Richmond, NYNYISO Sep 2024target 2028
Onshore wind project J3597, Lonoke County
Onshore wind
348 MWIn study Lonoke, ARMISO Apr 2024target 2028
HyFuels Green Lake Solar
Solar · HyFuels Green Lake Solar LLC
347 MWIn study Victoria, TXERCOT Sep 2022target 2027
Other project Q91, Los Angeles County
Other
346 MWIn study Los Angeles, CAWest Jun 2022target 2030
Hydro project G0490, Douglas County
Hydro
345 MWIn study Douglas, WAWest Jul 2013target 2022
Onshore wind project Q347, Navajo County
Onshore wind
345 MWIn study Navajo, AZWest Sep 2020target 2024
Solar project GEN-2024-046, Hansford County
Solar
345 MWIn study Hansford, TXSPP Oct 2024target 2029
Page 28 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)