🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Nevada

SOLAR + STORAGE · WEST

Solar + storage project Company OA, Humboldt County

Solar + storage project Company OA, Humboldt County is a 350 MW solar + storage request suspended in the West interconnection queue, in Humboldt County, Nevada, connecting to NV Energy.

Queue statusPaused / redesign
  1. PlanningQueued Sep 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Company OA
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Humboldt County, Nevada
Technology
Solar: 350 MW · Battery
Total requested
350 MW
Service type
NRIS and ERIS
Queue status
Suspended
Entered queue
29 September 2022
Proposed online date
December 2030

Location

Marker shows the centre of Humboldt County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Humboldt County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem