United States › Grid › Interconnection queues › Nevada

SOLAR · WEST

Solar project Company IF, Humboldt County

Solar project Company IF, Humboldt County is a 350 MW solar request with a signed interconnection agreement in the West interconnection queue, in Humboldt County, Nevada, connecting to NV Energy.

Queue statusConsented
  1. PlanningQueued Mar 2018 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
Company IF
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Humboldt County, Nevada
Technology
Solar: 350 MW
Total requested
350 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Active
Entered queue
19 March 2018
Proposed online date
February 2026

Location

Marker shows the centre of Humboldt County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Humboldt County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem