United States › Grid › Interconnection queues › Wyoming
BATTERY STORAGE · WESTBattery storage project S0026, Converse County
Battery storage project S0026, Converse County is a 350 MW battery storage request in interconnection study in the West interconnection queue, in Converse County, Wyoming, connecting to PacifiCorp.
Queue statusIn planning
- PlanningQueued Feb 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- S0026
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Connection point (POI)
- Yellowcake substation
- Location
- Converse County, Wyoming
- Technology
- Battery: 350 MW
- Total requested
- 350 MW
- Service type
- Energy only (ERIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Active
- Entered queue
- 8 February 2024
- Proposed online date
- June 2026
Location
Marker shows the centre of Converse County; the queue data does not give exact sites.
Other requests in Converse County
- Solar project CLPT G18, Converse CountySolar · 255 MW · agreement signed
- Onshore wind project C2-12, Converse CountyOnshore wind · 42.0 MW · agreement signed
- Gas project T2-017, Converse CountyGas · 600 MW · in study
- Battery storage project S0028, Converse CountyBattery storage · 320 MW · in study
- Solar project S0003, Converse CountySolar · 237 MW · in study
- Solar + storage project C3-038, Converse CountySolar + storage · 199 MW · in study
- Onshore wind project C2-49, Converse CountyOnshore wind · 150 MW · in study
- Battery storage project S0038, Converse CountyBattery storage · 80.0 MW · in study
- Onshore wind project PIS051, Converse CountyOnshore wind · 42.0 MW · in study
- Solar + storage project GI-DISIS-2021-10, Converse CountySolar + storage · 398 MW · suspended
- Onshore wind project 712, Converse CountyOnshore wind · 520 MW · built
- Onshore wind project 713, Converse CountyOnshore wind · 350 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem