United States › Grid › Interconnection queues › Wyoming

SOLAR + STORAGE · WEST

Solar + storage project C3-038, Converse County

Solar + storage project C3-038, Converse County is a 199 MW solar + storage request in interconnection study in the West interconnection queue, in Converse County, Wyoming, connecting to PacifiCorp.

Queue statusIn planning
  1. PlanningQueued May 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jul 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
C3-038
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Casper substation
Location
Converse County, Wyoming
Technology
Solar: 199 MW · Battery
Total requested
199 MW
Service type
Network resource (NRIS)
Queue status
Active
Entered queue
8 May 2023
Proposed online date
July 2027

Location

Marker shows the centre of Converse County; the queue data does not give exact sites.

Power plants in Wyoming · Transmission lines in Wyoming

Other requests in Converse County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem