United States › Grid › Interconnection queues › Texas
SOLAR · SPPSolar project GEN-2024-046, Hansford County
Solar project GEN-2024-046, Hansford County is a 345 MW solar request in interconnection study in the SPP interconnection queue, in Hansford County, Texas, connecting to SPS.
Queue statusIn planning
- PlanningQueued Oct 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GEN-2024-046
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- SPS
- Connection point (POI)
- Hitchland-Moore 230 kV line
- Location
- Hansford County, Texas
- Technology
- Solar: 345 MW
- Total requested
- 345 MW
- Service type
- NRIS and ERIS
- Study phase
- DISIS STAGE
- Queue status
- Active
- Entered queue
- 30 October 2024
- Proposed online date
- December 2029
Location
Marker shows the centre of Hansford County; the queue data does not give exact sites.
Other requests in Hansford County
- Battery storage project GEN-2023-SR8, Hansford CountyBattery storage · 200 MW · agreement signed
- Solar project GEN-2024-045, Hansford CountySolar · 345 MW · in study
- Battery storage project GEN-2026-PR4, Hansford CountyBattery storage · 132 MW · in study
- Onshore wind project GEN-2025-SR2, Hansford CountyOnshore wind · 67.2 MW · in study
- Onshore wind project GEN-2006-044, Hansford CountyOnshore wind · 370 MW · built
- Onshore wind project GEN-2010-014, Hansford CountyOnshore wind · 359 MW · built
- Onshore wind project GEN-2011-022, Hansford CountyOnshore wind · 299 MW · built
- Onshore wind project GEN-2002-008, Hansford CountyOnshore wind · 240 MW · built
- Onshore wind project GEN-2002-009, Hansford CountyOnshore wind · 67.2 MW · built
- Onshore wind project GEN-2006-020S, Hansford CountyOnshore wind · 20.0 MW · built
- Other project GEN-2022-112, Hansford CountyOther · 370 MW · withdrawn
- Onshore wind project GEN-2007-042, Hansford CountyOnshore wind · 360 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem