ONSHORE WIND · SPP

Onshore wind project GEN-2002-009, Hansford County

Onshore wind project GEN-2002-009, Hansford County is a 67.2 MW onshore wind request built and operating in the SPP interconnection queue, in Hansford County, Texas, connecting to SPS.

Queue statusOperating
  1. PlanningQueued Jul 2002 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingSep 2006 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2002-009
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
Hansford 115kV
Location
Hansford County, Texas
Technology
Wind: 67.2 MW
Total requested
67.2 MW
Service type
Energy only (ERIS)
Study phase
IA FULLY EXECUTED/COMMERCIAL OPERATION
Queue status
Operational
Entered queue
19 July 2002
Proposed online date
September 2006
Came online
September 2006

Location

Marker shows the centre of Hansford County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Hansford County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem