Solar project GEN-2020-084, Burt County

Solar project GEN-2020-084, Burt County is a 350 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Burt County, Nebraska, connecting to OPPD.

Queue statusConsented
  1. PlanningQueued Apr 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2030 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GEN-2020-084
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OPPD
Connection point (POI)
Raun - Fort Calhoun 345 kV
Location
Burt County, Nebraska
Technology
Solar: 350 MW
Total requested
350 MW
Service type
NRIS and ERIS
Study phase
IA FULLY EXECUTED/ON SCHEDULE
Queue status
Active
Entered queue
30 April 2020
Proposed online date
February 2030

Location

Marker shows the centre of Burt County; the queue data does not give exact sites.

Power plants in Nebraska · Transmission lines in Nebraska

Other requests in Burt County