United States › Grid › Interconnection queues › Nebraska
SOLAR · SPPSolar project GEN-2020-084, Burt County
Solar project GEN-2020-084, Burt County is a 350 MW solar request with a signed interconnection agreement in the SPP interconnection queue, in Burt County, Nebraska, connecting to OPPD.
Queue statusConsented
- PlanningQueued Apr 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Feb 2030 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- GEN-2020-084
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OPPD
- Connection point (POI)
- Raun - Fort Calhoun 345 kV
- Location
- Burt County, Nebraska
- Technology
- Solar: 350 MW
- Total requested
- 350 MW
- Service type
- NRIS and ERIS
- Study phase
- IA FULLY EXECUTED/ON SCHEDULE
- Queue status
- Active
- Entered queue
- 30 April 2020
- Proposed online date
- February 2030
Location
Marker shows the centre of Burt County; the queue data does not give exact sites.
Other requests in Burt County
- Solar project GEN-2018-043, Burt CountySolar · 500 MW · agreement signed
- Onshore wind project GEN-2017-105, Burt CountyOnshore wind · 75.0 MW · agreement signed
- Solar project GEN-2024-234, Burt CountySolar · 200 MW · in study
- Solar project GEN-2023-202, Burt CountySolar · 150 MW · withdrawn
- Battery storage project GEN-2022-153, Burt CountyBattery storage · 100 MW · withdrawn
- Onshore wind project GEN-2008-125O, Burt CountyOnshore wind · 80.0 MW · withdrawn
- Battery storage project GEN-2019-071, Burt CountyBattery storage · 51.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem