United States βΊ Grid βΊ Interconnection queues βΊ Nebraska
BATTERY STORAGE Β· SPPBattery storage project GEN-2022-153, Burt County
Battery storage project GEN-2022-153, Burt County is a 100 MW battery storage request withdrawn in the SPP interconnection queue, in Burt County, Nebraska, connecting to NPPD.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2023 (completed)
- Withdrawn / abandonedNov 2023 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2022-153
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- NPPD
- Connection point (POI)
- Tekamah 161 kV Substation
- Location
- Burt County, Nebraska
- Technology
- Battery: 100 MW
- Total requested
- 100 MW
- Service type
- NRIS and ERIS
- Study phase
- WITHDRAWN
- Queue status
- Withdrawn
- Entered queue
- 24 February 2023
- Proposed online date
- August 2026
- Withdrawn
- November 2023
Location
Marker shows the centre of Burt County; the queue data does not give exact sites.
Other requests in Burt County
- Solar project GEN-2018-043, Burt CountySolar Β· 500 MW Β· agreement signed
- Solar project GEN-2020-084, Burt CountySolar Β· 350 MW Β· agreement signed
- Onshore wind project GEN-2017-105, Burt CountyOnshore wind Β· 75.0 MW Β· agreement signed
- Solar project GEN-2024-234, Burt CountySolar Β· 200 MW Β· in study
- Solar project GEN-2023-202, Burt CountySolar Β· 150 MW Β· withdrawn
- Onshore wind project GEN-2008-125O, Burt CountyOnshore wind Β· 80.0 MW Β· withdrawn
- Battery storage project GEN-2019-071, Burt CountyBattery storage Β· 51.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem