Solar project GEN-2023-202, Burt County is a 150 MW solar request withdrawn in the SPP interconnection queue, in Burt County, Nebraska, connecting to OPPD.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2023 (completed)
  2. Withdrawn / abandonedApr 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2023-202
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OPPD
Connection point (POI)
Tekamah - Raun 161 kV Line
Location
Burt County, Nebraska
Technology
Solar: 150 MW
Total requested
150 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
2 October 2023
Proposed online date
December 2027
Withdrawn
April 2024

Location

Marker shows the centre of Burt County; the queue data does not give exact sites.