SOLAR + STORAGE · SPP

Solar + storage project ERAS-2025-030, Chaves County

Solar + storage project ERAS-2025-030, Chaves County is a 350 MW solar + storage request in interconnection study in the SPP interconnection queue, in Chaves County, New Mexico, connecting to SPS.

Queue statusIn planning
  1. PlanningQueued Oct 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
ERAS-2025-030
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SPS
Connection point (POI)
G24-279 New Switch Station tying into Chaves - Eddy County 230 kV Line
Location
Chaves County, New Mexico
Technology
Solar: 350 MW · Battery
Total requested
350 MW
Service type
NRIS and ERIS
Study phase
ERAS
Queue status
Active
Entered queue
2 October 2025
Proposed online date
October 2030

Location

Marker shows the centre of Chaves County; the queue data does not give exact sites.

Power plants in New Mexico · Transmission lines in New Mexico

Other requests in Chaves County