Other project Q91, Los Angeles County

Other project Q91, Los Angeles County is a 346 MW other request in interconnection study in the West interconnection queue, in Los Angeles County, California, connecting to Los Angeles Department of Water and Power.

Queue statusIn planning
  1. PlanningQueued Jun 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q91
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Connection point (POI)
Scattergood 138kV Switchyard
Location
Los Angeles County, California
Technology
Hydrogen: 346 MW
Total requested
346 MW
Study phase
Application received
Queue status
Active
Entered queue
16 June 2022
Proposed online date
January 2030

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Los Angeles County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem