Big SKY Solar

Big SKY Solar is a 476 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Los Angeles County, California, connecting to SCE.

Queue statusConsented
  1. PlanningQueued Mar 2011 (completed)
  2. ConsentedSep 2014 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2023 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
768
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Antelope Substation 230kV bus
Location
Los Angeles County, California
Technology
Solar: 320 MW · Battery: 156 MW
Total requested
476 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
31 March 2011
Agreement signed
10 September 2014
Proposed online date
January 2023

Location

Marker shows the centre of Los Angeles County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California