United States › Grid › Interconnection queues › Iowa
GAS · MISOGas project J2945, Washington County
Gas project J2945, Washington County is a 350 MW gas request in interconnection study in the MISO interconnection queue, in Washington County, Iowa, connecting to AMEREN MISSOURI.
Queue statusIn planning
- PlanningQueued Sep 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Apr 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- J2945
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN MISSOURI
- Connection point (POI)
- SUB T 3 - HILLS 3 345.0kV
- Location
- Washington County, Iowa
- Technology
- Gas: 350 MW
- Total requested
- 350 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: DPP 2; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 15 September 2022
- Proposed online date
- April 2027
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Other requests in Washington County
- Gas project J4114, Washington CountyGas · 525 MW · in study
- Solar project J2002, Washington CountySolar · 200 MW · in study
- Onshore wind project R50, Washington CountyOnshore wind · 501 MW · withdrawn
- Onshore wind project G973, Washington CountyOnshore wind · 501 MW · withdrawn
- Onshore wind project J154, Washington CountyOnshore wind · 500 MW · withdrawn
- Onshore wind project J192, Washington CountyOnshore wind · 500 MW · withdrawn
- Onshore wind project J2363, Washington CountyOnshore wind · 226 MW · withdrawn
- Onshore wind project J981, Washington CountyOnshore wind · 200 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem