United States βΊ Grid βΊ Interconnection queues βΊ Iowa
ONSHORE WIND Β· MISOOnshore wind project J981, Washington County
Onshore wind project J981, Washington County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Washington County, Iowa, connecting to MIDAMERICAN ENERGY COMPANY.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2018 (completed)
- Withdrawn / abandonedMar 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J981
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- MIDAMERICAN ENERGY COMPANY
- Connection point (POI)
- Sub T 345kV Substation
- Location
- Washington County, Iowa
- Technology
- Wind: 200 MW
- Total requested
- 200 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Withdrawn
- Entered queue
- 12 March 2018
- Proposed online date
- March 2021
- Withdrawn
- March 2021
Location
Marker shows the centre of Washington County; the queue data does not give exact sites.
Other requests in Washington County
- Gas project J4114, Washington CountyGas Β· 525 MW Β· in study
- Gas project J2945, Washington CountyGas Β· 350 MW Β· in study
- Solar project J2002, Washington CountySolar Β· 200 MW Β· in study
- Onshore wind project R50, Washington CountyOnshore wind Β· 501 MW Β· withdrawn
- Onshore wind project G973, Washington CountyOnshore wind Β· 501 MW Β· withdrawn
- Onshore wind project J154, Washington CountyOnshore wind Β· 500 MW Β· withdrawn
- Onshore wind project J192, Washington CountyOnshore wind Β· 500 MW Β· withdrawn
- Onshore wind project J2363, Washington CountyOnshore wind Β· 226 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem