πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project J192, Washington County

Onshore wind project J192, Washington County is a 500 MW onshore wind request withdrawn in the MISO interconnection queue, in Washington County, Iowa.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2011 (completed)
  2. Withdrawn / abandonedMay 2012 (project stopped here)
  3. ConsentedMay 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J192
Grid region
MISO (Midcontinent)
Connection point (POI)
Hills - Sub T 345 kV
Location
Washington County, Iowa
Technology
Wind: 500 MW
Total requested
500 MW
Study phase
SPA - SIS
Queue status
Withdrawn
Entered queue
31 January 2011
Agreement signed
17 May 2012
Proposed online date
December 2012
Withdrawn
May 2012

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Washington County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem