Solar project J2002, Washington County

Solar project J2002, Washington County is a 200 MW solar request in interconnection study in the MISO interconnection queue, in Washington County, Iowa, connecting to MIDAMERICAN ENERGY CO..

Queue statusIn planning
  1. PlanningQueued Aug 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2002
Grid region
MISO (Midcontinent)
Utility / transmission owner
MIDAMERICAN ENERGY CO.
Connection point (POI)
SUB T HASKINS
Location
Washington County, Iowa
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Active
Entered queue
13 August 2021
Proposed online date
March 2024

Location

Marker shows the centre of Washington County; the queue data does not give exact sites.