🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Nevada

SOLAR + STORAGE · WEST

Solar + storage project Company JX, Pershing County

Solar + storage project Company JX, Pershing County is a 340 MW solar + storage request suspended in the West interconnection queue, in Pershing County, Nevada, connecting to NV Energy.

Queue statusPaused / redesign
  1. PlanningQueued Sep 2019 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Company JX
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Pershing County, Nevada
Technology
Solar: 340 MW · Battery
Total requested
340 MW
Service type
NRIS and ERIS
Queue status
Suspended
Entered queue
23 September 2019
Proposed online date
March 2023

Location

Marker shows the centre of Pershing County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Pershing County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem