🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Nevada

SOLAR + STORAGE · WEST

Solar + storage project Company QC, Pershing County

Solar + storage project Company QC, Pershing County is a 200 MW solar + storage request in interconnection study in the West interconnection queue, in Pershing County, Nevada, connecting to NV Energy.

Queue statusIn planning
  1. PlanningQueued Mar 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Company QC
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Pershing County, Nevada
Technology
Solar: 200 MW · Battery
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
23 March 2023
Proposed online date
January 2026

Location

Marker shows the centre of Pershing County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Pershing County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem