United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA — page 23

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 23 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Dorado Solar
Solar · Enbridge Solar (Sequoia I), LLC
401 MWAgreement signed Callahan, TXERCOT Jan 2020target 2026
Onshore wind project GEN-2024-102, Finney County
Onshore wind
401 MWIn study Finney, KSSPP Mar 2025target 2031
Onshore wind project GEN-2024-109, Bailey County
Onshore wind
401 MWIn study Bailey, TXSPP Mar 2025target 2031
Onshore wind project T2-057, Carbon County
Onshore wind
400 MWIn study Carbon, WYWest Sep 2025target 2029
Onshore wind project GEN-2017-183, Hodgeman County
Onshore wind
400 MWAgreement signed Hodgeman, KSSPP Nov 2017target 2029
Battery storage project Company 212, Clark County
Battery storage
400 MWPaused / redesign Clark, NVWest Mar 2022target 2029
Other project Q581, Maricopa County
Other
400 MWIn study Maricopa, AZWest May 2025target 2031
Battery storage project J2496, White County
Battery storage
400 MWIn study White, INMISO Sep 2022target 2026
Solar project J2268, Linn County
Solar
400 MWIn study Linn, IAMISO Aug 2021target 2024
Onshore wind project GI-2006-1g, Logan County
Onshore wind
400 MWAgreement signed Logan, COWest Jan 2006target 2007
Solar + storage project Company KU, Lyon County
Solar + storage
400 MWAgreement signed Lyon, NVWest Sep 2020target 2025
Solar + storage project 787, Emery County
Solar + storage · Green River Solar I, LLC
400 MWAgreement signed Emery, UTWest Aug 2016target 2024
Solar + storage project 2023-G1
Solar + storage
400 MWIn study West Oct 2022target 2025
Solar + storage project G0744, Grant County
Solar + storage
400 MWIn study Grant, WAWest May 2022target 2026
Mount Laguna Wind 2
Onshore wind
400 MWAgreement signed San Diego, CACAISO May 2017target 2031
Other project SC1Q31, Sacramento County
Other
400 MWIn study Sacramento, CAWest Jul 2025target 2032
Solar + storage project Company MW, White Pine County
Solar + storage
400 MWAgreement signed White Pine, NVWest Mar 2022target 2030
Battery storage project 21-104, Washington County
Battery storage
400 MWAgreement signed Washington, ORWest Aug 2021target 2028
Battery storage project 620, Bay County
Battery storage · FPL
400 MWIn study Bay, FLSoutheast Jan 2024target 2026
Solar project G1035, Douglas County
Solar
400 MWIn study Douglas, WAWest Nov 2023target 2028
Battery storage project J4076, Jefferson Davis Parish County
Battery storage
400 MWIn study Jefferson Davis Parish, LAMISO Oct 2025target 2030
Solar + storage project GEN-2021-090, Yoakum County
Solar + storage
400 MWIn study Yoakum, TXSPP Apr 2021target 2028
Solar project J2088, Lee County
Solar
400 MWIn study Lee, ARMISO Jul 2022target 2027
Gridline Solar
Solar · Big Lake Ranch LLC
400 MWIn study Crockett, TXERCOT Aug 2025target 2029
Battery storage project IC-1102, Montgomery County
Battery storage
400 MWPaused / redesign Montgomery, ALSoutheast Dec 2022target 2026
Driftwood Stella
Solar + storage
400 MWAgreement signed Kern, CACAISO May 2017target 2026
Battery storage project Q116, Clark County
Battery storage
400 MWIn study Clark, NVWest Nov 2025target 2032
Solar + storage project C1-44, Lake County
Solar + storage · Archway Solar Energy LLC
400 MWPaused / redesign Lake, ORWest May 2021target 2025
Solar + storage project Q537, Pinal County
Solar + storage
400 MWIn study Pinal, AZWest Sep 2023target 2027
Onshore wind project GI-2023-14, Morgan County
Onshore wind
400 MWPaused / redesign Morgan, COWest May 2023target 2026
Gamay
Solar + storage
400 MWIn study Kern, CACAISO Apr 2023target 2031
Battery storage project 25-00384, Clark County
Battery storage
400 MWIn study Clark, NVWest Jul 2025target 2029
Solar + storage project GI-2024-05, Pueblo County
Solar + storage
400 MWIn study Pueblo, COWest Apr 2024target 2028
Aratina Solar Center 2
Solar + storage
400 MWAgreement signed Kern, CACAISO Apr 2019target 2026
Solar + storage project Company 194, Clark County
Solar + storage
400 MWAgreement signed Clark, NVWest Mar 2021target 2023
Onshore wind project J1026, Audrain County
Onshore wind
400 MWAgreement signed Audrain, MOMISO Mar 2018target 2023
Vaquero 1 Wind
Onshore wind · Enerverse
400 MWIn study Zapata, TXERCOT Apr 2016target 2027
Battery storage project IA-PNM-2025-09, Valencia County
Battery storage
400 MWIn study Valencia, NMWest Mar 2025target 2029
Onshore wind project 367, Rosebud County
Onshore wind
400 MWPaused / redesign Rosebud, MTWest Sep 2019target 2022
Battery storage project J2304, Columbia County
Battery storage
400 MWIn study Columbia, WIMISO Dec 2021target 2024
Gas project 5RSC-2024-02, Weld County
Gas
400 MWIn study Weld, COWest Jan 2024target 2027
Oak Run Solar Project
Solar
400 MWAgreement signed Madison, OHPJM Aug 2020target 2030
Onshore wind project C2-106, Lincoln County
Onshore wind
400 MWIn study Lincoln, WYWest May 2022target 2025
Wind + storage project Company MX, Lyon County
Wind + storage
400 MWPaused / redesign Lyon, NVWest Mar 2022target 2027
Battery storage project 23-221, Washington County
Battery storage
400 MWIn study Washington, ORWest Mar 2023target 2027
Sequoia
Solar + storage
400 MWIn study Tulare, CACAISO Apr 2020target 2031
Brushy
Battery storage
400 MWIn study Solano, CACAISO Apr 2021target 2031
Solar project J2931, Henderson County
Solar
400 MWIn study Henderson, KYMISO Sep 2022target 2025
Rexford 2 Solar Farm
Solar + storage
400 MWAgreement signed Tulare, CACAISO Apr 2020target 2027
Solar + storage project J2302, St. Helena Parish County
Solar + storage
400 MWIn study St. Helena Parish, LAMISO Nov 2021target 2027
Page 23 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)