United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Dorado Solar

Dorado Solar is a 401 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Callahan County, Texas.

Queue statusConsented
  1. PlanningQueued Jan 2020 (completed)
  2. ConsentedJun 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Feb 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0261
Grid region
ERCOT (Texas)
Developer
Enbridge Solar (Sequoia I), LLC
Connection point (POI)
68051 Reata 345kV
Location
Callahan County, Texas
Technology
Solar: 401 MW
Total requested
401 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
9 January 2020
Agreement signed
19 June 2023
Proposed online date
February 2026

Location

Marker shows the centre of Callahan County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Callahan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem