ONSHORE WIND Β· ERCOT

Century Oak Wind

Century Oak Wind is a 126 MW onshore wind request withdrawn in the ERCOT interconnection queue, in Callahan County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2018 (completed)
  2. Withdrawn / abandonedJun 2022 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
20INR0048
Grid region
ERCOT (Texas)
Developer
Engie
Connection point (POI)
6670 Putnam 138kV
Location
Callahan County, Texas
Technology
Wind: 126 MW
Total requested
126 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
28 January 2018
Proposed online date
June 2023
Withdrawn
June 2022

Location

Marker shows the centre of Callahan County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Callahan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem