United States › Grid › Interconnection queues › Texas

SOLAR · ERCOT

Sequoia II Solar

Sequoia II Solar is a 418 MW solar request with a signed interconnection agreement in the ERCOT interconnection queue, in Callahan County, Texas.

Queue statusConsented
  1. PlanningQueued Jan 2020 (completed)
  2. ConsentedAug 2023 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
22INR0262
Grid region
ERCOT (Texas)
Developer
Deville Solar LLC
Connection point (POI)
68051 Reata 345kV
Location
Callahan County, Texas
Technology
Solar: 418 MW
Total requested
418 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
22 January 2020
Agreement signed
29 August 2023
Proposed online date
November 2026

Location

Marker shows the centre of Callahan County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Callahan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem