Battery storage project Q116, Clark County

Battery storage project Q116, Clark County is a 400 MW battery storage request in interconnection study in the West interconnection queue, in Clark County, Nevada, connecting to Los Angeles Department of Water and Power.

Queue statusIn planning
  1. PlanningQueued Nov 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2032 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
Q116
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Connection point (POI)
McCullough 500kV Substation
Location
Clark County, Nevada
Technology
Battery: 400 MW
Total requested
400 MW
Study phase
Application received
Queue status
Active
Entered queue
5 November 2025
Proposed online date
December 2032

Location

Marker shows the centre of Clark County; the queue data does not give exact sites.