ONSHORE WIND · ERCOTVaquero 1 Wind
Vaquero 1 Wind is a 400 MW onshore wind request in interconnection study in the ERCOT interconnection queue, in Zapata County, Texas.
Queue statusIn planning
- PlanningQueued Apr 2016 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jan 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 17INR0043
- Grid region
- ERCOT (Texas)
- Developer
- Enerverse
- Connection point (POI)
- tap 345kV 8905 N Edinb - 8455 Lon Hill
- Location
- Zapata County, Texas
- Technology
- Wind: 400 MW
- Total requested
- 400 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 1 April 2016
- Proposed online date
- January 2027
Location
Marker shows the centre of Zapata County; the queue data does not give exact sites.
Other requests in Zapata County
- Cascabel Wind 2Onshore wind · 198 MW · agreement signed
- Cascabel Wind 1Onshore wind · 198 MW · agreement signed
- Corralitos Wind 1Onshore wind · 196 MW · agreement signed
- Corralitos Wind 2Onshore wind · 195 MW · agreement signed
- Falcon BESSBattery storage · 517 MW · in study
- Freedom Falcon BESSBattery storage · 502 MW · in study
- Tetris SolarSolar · 359 MW · in study
- Sierra Madre SolarSolar · 255 MW · in study
- Zelus BESSBattery storage · 201 MW · in study
- Falcon Zapata Storage 138Battery storage · 201 MW · in study
- Barrosos Creek Wind 3Onshore wind · 198 MW · in study
- Barrosos Creek Wind 4Onshore wind · 198 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem