United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTCorralitos Wind 1
Corralitos Wind 1 is a 196 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Zapata County, Texas.
Queue statusConsented
- PlanningQueued Jan 2023 (completed)
- ConsentedJun 2025 (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 24INR0505
- Grid region
- ERCOT (Texas)
- Developer
- Vaquero Wind Energy, LLC
- Connection point (POI)
- Tap 345kV 80225 CENIZO7C - 80307 DELSOL7C (New ETT Tiempo Substation)
- Location
- Zapata County, Texas
- Technology
- Wind: 196 MW
- Total requested
- 196 MW
- Study phase
- SS Completed, FIS Started, IA
- Queue status
- Active
- Entered queue
- 30 January 2023
- Agreement signed
- 19 June 2025
- Proposed online date
- December 2027
Location
Marker shows the centre of Zapata County; the queue data does not give exact sites.
Other requests in Zapata County
- Cascabel Wind 2Onshore wind · 198 MW · agreement signed
- Cascabel Wind 1Onshore wind · 198 MW · agreement signed
- Corralitos Wind 2Onshore wind · 195 MW · agreement signed
- Falcon BESSBattery storage · 517 MW · in study
- Freedom Falcon BESSBattery storage · 502 MW · in study
- Vaquero 1 WindOnshore wind · 400 MW · in study
- Tetris SolarSolar · 359 MW · in study
- Sierra Madre SolarSolar · 255 MW · in study
- Zelus BESSBattery storage · 201 MW · in study
- Falcon Zapata Storage 138Battery storage · 201 MW · in study
- Barrosos Creek Wind 3Onshore wind · 198 MW · in study
- Barrosos Creek Wind 4Onshore wind · 198 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem