ONSHORE WIND · ERCOT

Cascabel Wind 2

Cascabel Wind 2 is a 198 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Zapata County, Texas.

Queue statusConsented
  1. PlanningQueued Mar 2023 (completed)
  2. ConsentedMay 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0561
Grid region
ERCOT (Texas)
Developer
Vaquero Wind Energy, LLC
Connection point (POI)
345 kV Rapido Substation (New ETT Substation) tapping the existing 345 kV Line from CENIZO7C (#80225) to DELSOL7C (#80307).
Location
Zapata County, Texas
Technology
Wind: 198 MW
Total requested
198 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
13 March 2023
Agreement signed
23 May 2025
Proposed online date
December 2027

Location

Marker shows the centre of Zapata County; the queue data does not give exact sites.