Solar + storage project 787, Emery County

Solar + storage project 787, Emery County is a 400 MW solar + storage request with a signed interconnection agreement in the West interconnection queue, in Emery County, Utah, connecting to PacifiCorp.

Queue statusConsented
  1. PlanningQueued Aug 2016 (completed)
  2. ConsentedMay 2019 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2024 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
787
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Green River Solar I, LLC
Connection point (POI)
Emery-Sigurd #2 line
Location
Emery County, Utah
Technology
Solar: 400 MW · Battery
Total requested
400 MW
Service type
Energy only (ERIS)
Study phase
IA executed 5/13/19, LGIA combined with Q0788
Queue status
Active
Entered queue
8 August 2016
Agreement signed
13 May 2019
Proposed online date
November 2024

Location

Marker shows the centre of Emery County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Emery County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem