Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 19 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Solar + storage project NC5-001, Kane County
Solar + storage
480 MWIn study Kane, UTWest May 2015target 2028
Onshore wind project J3966, Huron County
Onshore wind
480 MWIn study Huron, MIMISO Apr 2025target 2029
Pluot
Solar + storage
479 MWAgreement signed Kings, CACAISO May 2016target 2026
North Royal Thermal (TEF- Due Diligence)
Gas · Invenergy Energy Transition Development LLC
479 MWIn study Lamar, TXERCOT Jun 2024target 2030
Pomegranate
Solar + storage
479 MWAgreement signed Kings, CACAISO May 2016target 2025
Other project J3163, Cass County
Other
479 MWIn study Cass, NDMISO Jul 2022target 2028
Mirando Valley Wind
Onshore wind · ACE DevCo NC LLC
479 MWIn study Jim Hogg, TXERCOT Aug 2024target 2028
Gas project E0032, San Jacinto County
Gas · Entergy Texas, Inc.
478 MWIn study San Jacinto, TXMISO Aug 2025target 2027
Gas project GEN-2023-222, Gage County
Gas
478 MWIn study Gage, NESPP Oct 2023target 2030
Waterford 5
Gas · Entergy Louisiana, LLC
478 MWIn study St. Charles Parish, LAMISO Aug 2025target 2028
Gas project GEN-2023-224, Lancaster County
Gas
478 MWIn study Lancaster, NESPP Oct 2023target 2029
Onshore wind project Q273, Navajo County
Onshore wind
477 MWIn study Navajo, AZWest Mar 2018target 2021
Big SKY Solar
Solar + storage
476 MWAgreement signed Los Angeles, CACAISO Mar 2011target 2023
Corby 2
Battery storage
476 MWIn study Solano, CACAISO Apr 2021target 2031
Coal project BHBE G11, Campbell County
Coal
475 MWAgreement signed Campbell, SDWest Sep 2011target 2011
Solar + storage project GEN-2023-102, Woods County
Solar + storage
475 MWIn study Woods, OKSPP Oct 2023target 2029
Alkali Creek Wind
Onshore wind · Alkali Creek Wind, LLC
474 MWIn study Fisher, TXERCOT Aug 2025target 2028
Serenity Wind
Onshore wind · Serenity Wind, LLC
473 MWIn study Armstrong, TXERCOT Mar 2025target 2028
Gas project GEN-2024-343, Harrison County
Gas
471 MWIn study Harrison, TXSPP Mar 2025target 2030
Gas project J4021, Sullivan County
Gas
470 MWIn study Sullivan, INMISO May 2025target 2028
Gas project J3331, Sullivan County
Gas
470 MWIn study Sullivan, INMISO Apr 2024target 2028
Solar project IC-1084, Coweta County
Solar
470 MWPaused / redesign Coweta, GASoutheast Oct 2022target 2027
Gregory Power Development SLF
Gas · Gregory Power Partners LLC
470 MWIn study San Patricio, TXERCOT Nov 2024target 2028
Baker Branch Solar
Solar · Mockingbird Solar Center, LLC
469 MWAgreement signed Lamar, TXERCOT Mar 2020target 2026
Solar + storage project 2021-G4, Pinal County
Solar + storage
463 MWIn study Pinal, AZWest Apr 2021target 2023
Shoals Energy Storage 2
Battery storage
461 MWIn study Los Angeles, CACAISO Apr 2023target 2029
Gas project GI-129, Payne County
Gas
460 MWIn study Payne, OKSoutheast Jul 2025target 2030
Gas project GI-104, Payne County
Gas
460 MWAgreement signed Payne, OKSoutheast Jul 2022target 2026
Hollow Branch Creek Storage
Solar + storage · Hollow Branch Creek Solar LLC
460 MWIn study Leon, TXERCOT Sep 2022target 2027
Gas project GI-132, Butler County
Gas
460 MWIn study Butler, MOSoutheast Jul 2025target 2030
Gas project GI-130, Payne County
Gas
460 MWIn study Payne, OKSoutheast Jul 2025target 2030
Gas project GI-103, Creek County
Gas
460 MWAgreement signed Creek, OKSoutheast Jul 2022target 2027
Hollow Branch Creek Solar
Solar + storage · Hollow Branch Creek Solar LLC
460 MWAgreement signed Leon, TXERCOT Sep 2022target 2027
Gas project GI-131, Randolph County
Gas
460 MWIn study Randolph, MOSoutheast Jul 2025target 2030
Gas project GI-126, Randolph County
Gas
460 MWIn study Randolph, MOSoutheast Jan 2025target 2029
Gas project GI-128, Clinton County
Gas
460 MWIn study Clinton, MOSoutheast Jul 2025target 2030
Gas project GI-121, Randolph County
Gas
460 MWAgreement signed Randolph, MOSoutheast May 2024target 2030
Solar + storage project Company 218, Clark County
Solar + storage
460 MWPaused / redesign Clark, NVWest Mar 2023target 2029
Gas project GI-101, Clinton County
Gas
460 MWAgreement signed Clinton, MOSoutheast Jul 2022target 2027
Gas project 301, Colleton County
Gas
458 MWIn study Colleton, SCSoutheast May 2025target 2032
Gas project 300, Colleton County
Gas
458 MWIn study Colleton, SCSoutheast May 2025target 2032
Red Butte Wind
Onshore wind · Red Butte Wind, LLC
457 MWIn study Morton, NDMISO Aug 2025target 2028
Gas project GEN-2024-247, Payne County
Gas
457 MWIn study Payne, OKSPP Mar 2025target 2030
NRG THW GT 345 (Tef)
Gas · NRG THW GT LLC
456 MWAgreement signed Harris, TXERCOT Nov 2022target 2026
Gas project 960889, Rowan County
Gas
455 MWIn study Rowan, NCSoutheast Jun 2024
Gas project 961188, Stokes County
Gas
455 MWIn study Stokes, NCSoutheast Jun 2024
Gas project 961210, Stokes County
Gas
455 MWIn study Stokes, NCSoutheast Jun 2024
Gas project 956747, Rowan County
Gas
455 MWIn study Rowan, SCSoutheast Jun 2024
Gas project E0037, Sheboygan County
Gas · Wisconsin Power and Light Company (WPL)
455 MWIn study Sheboygan, WIMISO Aug 2025target 2025
Gas project E0038, Winnebago County
Gas · Wisconsin Power and Light Company (WPL)
455 MWIn study Winnebago, WIMISO Aug 2025target 2025
Page 19 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)