United States › Grid › Interconnection queues › Texas
GAS · MISOGas project E0032, San Jacinto County
Gas project E0032, San Jacinto County is a 478 MW gas request in interconnection study in the MISO interconnection queue, in San Jacinto County, Texas, connecting to Entergy Texas, Inc..
Queue statusIn planning
- PlanningQueued Aug 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- E0032
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Entergy Texas, Inc.
- Developer
- Entergy Texas, Inc.
- Connection point (POI)
- Jancinto 230kV Substation
- Location
- San Jacinto County, Texas
- Technology
- Gas: 478 MW
- Total requested
- 478 MW
- Service type
- Network resource (NRIS)
- Study phase
- Request Status: Active; Post GIA Status: Not started
- Queue status
- Active
- Entered queue
- 6 August 2025
- Proposed online date
- October 2027
Location
Marker shows the centre of San Jacinto County; the queue data does not give exact sites.
Other requests in San Jacinto County
- Solar + storage project J2897, San Jacinto CountySolar + storage · 150 MW · in study
- Gas project J487, San Jacinto CountyGas · 999 MW · withdrawn
- Solar + storage project J2076, San Jacinto CountySolar + storage · 225 MW · withdrawn
- Solar project J1186, San Jacinto CountySolar · 100 MW · withdrawn
- Battery storage project J2235, San Jacinto CountyBattery storage · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem