Solar + storage project GEN-2023-102, Woods County

Solar + storage project GEN-2023-102, Woods County is a 475 MW solar + storage request in interconnection study in the SPP interconnection queue, in Woods County, Oklahoma, connecting to OGE.

Queue statusIn planning
  1. PlanningQueued Oct 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GEN-2023-102
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
OGE
Connection point (POI)
Degrasse 345 kV Substation
Location
Woods County, Oklahoma
Technology
Solar: 475 MW · Battery
Total requested
475 MW
Service type
NRIS and ERIS
Study phase
FACILITY STUDY STAGE
Queue status
Active
Entered queue
2 October 2023
Proposed online date
June 2029

Location

Marker shows the centre of Woods County; the queue data does not give exact sites.

Power plants in Oklahoma · Transmission lines in Oklahoma

Other requests in Woods County