United States βΊ Grid βΊ Interconnection queues βΊ Oklahoma
ONSHORE WIND Β· SPPOnshore wind project GEN-2015-095, Woods County
Onshore wind project GEN-2015-095, Woods County is a 176 MW onshore wind request withdrawn in the SPP interconnection queue, in Woods County, Oklahoma, connecting to OGE.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2015 (completed)
- Withdrawn / abandonedJan 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- OperatingJun 2020 (not reached)
- Closed (not reached)
Request details
- Queue ID
- GEN-2015-095
- Grid region
- SPP (Southwest Power Pool)
- Utility / transmission owner
- OGE
- Connection point (POI)
- Tap Mooreland - Knob Hill 138kV
- Location
- Woods County, Oklahoma
- Technology
- Wind: 176 MW
- Total requested
- 176 MW
- Service type
- Energy only (ERIS)
- Study phase
- TERMINATED
- Queue status
- Withdrawn
- Entered queue
- 21 September 2015
- Proposed online date
- June 2020
- Came online
- June 2020
- Withdrawn
- January 2024
Location
Marker shows the centre of Woods County; the queue data does not give exact sites.
Other requests in Woods County
- Solar project GEN-2019-045, Woods CountySolar Β· 155 MW Β· agreement signed
- Solar + storage project GEN-2023-102, Woods CountySolar + storage Β· 475 MW Β· in study
- Onshore wind project GEN-2024-135, Woods CountyOnshore wind Β· 250 MW Β· in study
- Onshore wind project GEN-2024-134, Woods CountyOnshore wind Β· 250 MW Β· in study
- Solar + storage project GEN-2023-104, Woods CountySolar + storage Β· 100 MW Β· in study
- Solar + storage project GEN-2023-100, Woods CountySolar + storage Β· 300 MW Β· withdrawn
- Battery storage project GEN-2019-046, Woods CountyBattery storage Β· 90.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem