United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Pomegranate

Pomegranate is a 479 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Kings County, California, connecting to PGAE.

Queue statusConsented
  1. PlanningQueued May 2016 (completed)
  2. ConsentedJan 2020 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
1243
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Gates 230 kV
Location
Kings County, California
Technology
Solar: 254 MW · Battery: 225 MW
Total requested
479 MW
Service type
Network resource (NRIS)
Study phase
Executed
Queue status
Active
Entered queue
2 May 2016
Agreement signed
7 January 2020
Proposed online date
December 2025

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kings County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem