United States › Grid › Interconnection queues › California
SOLAR + STORAGE · CAISOPluot
Pluot is a 479 MW solar + storage request with a signed interconnection agreement in the CAISO interconnection queue, in Kings County, California, connecting to PGAE.
Queue statusConsented
- PlanningQueued May 2016 (completed)
- ConsentedJan 2020 (current stage)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 1242
- Grid region
- CAISO (California)
- Utility / transmission owner
- PGAE
- Connection point (POI)
- Gates 230 kV
- Location
- Kings County, California
- Technology
- Solar: 254 MW · Battery: 225 MW
- Total requested
- 479 MW
- Service type
- Network resource (NRIS)
- Study phase
- Executed
- Queue status
- Active
- Entered queue
- 2 May 2016
- Agreement signed
- 7 January 2020
- Proposed online date
- June 2026
Location
Marker shows the centre of Kings County; the queue data does not give exact sites.
Power plants in California · Transmission lines in California
Other requests in Kings County
- Pelicans Jaw Hybrid SolarSolar + storage · 1,000 MW · agreement signed
- DaylightSolar + storage · 611 MW · agreement signed
- PomegranateSolar + storage · 479 MW · agreement signed
- American Kings SolarSolar + storage · 197 MW · agreement signed
- Kettleman Solar Project (Fka Kettleman Solar Farm)Solar + storage · 40.0 MW · agreement signed
- RippleSolar + storage · 1,880 MW · in study
- PlumSolar + storage · 1,560 MW · in study
- Valley Sunlight RefinerySolar + storage · 821 MW · in study
- SunglowSolar + storage · 744 MW · in study
- Blue StarSolar + storage · 513 MW · in study
- Maravillosa 1Solar + storage · 407 MW · in study
- MidBishopSolar + storage · 382 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem