United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Maravillosa 1

Maravillosa 1 is a 407 MW solar + storage request in interconnection study in the CAISO interconnection queue, in Kings County, California, connecting to PGAE.

Queue statusIn planning
  1. PlanningQueued Apr 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2029 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
2360
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
DRY LAKE SW STA 500 kV
Location
Kings County, California
Technology
Solar: 204 MW · Battery: 203 MW
Total requested
407 MW
Service type
Network resource (NRIS)
Study phase
Caiso Cluster 15 Unvalidated
Queue status
Active
Entered queue
17 April 2023
Proposed online date
June 2029

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kings County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem