🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

SOLAR + STORAGE · CAISO

Sunglow

Sunglow is a 744 MW solar + storage request in interconnection study in the CAISO interconnection queue, in Kings County, California, connecting to PG&E.

Queue statusIn planning
  1. PlanningQueued Apr 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
2260
Grid region
CAISO (California)
Utility / transmission owner
PG&E
Connection point (POI)
MANNING 500 kV
Location
Kings County, California
Technology
Solar: 372 MW · Battery: 372 MW
Total requested
744 MW
Service type
Network resource (NRIS)
Study phase
Caiso Cluster 15 Unvalidated
Queue status
Active
Entered queue
17 April 2023
Proposed online date
October 2030

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kings County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem