🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Utah

SOLAR + STORAGE · WEST

Solar + storage project NC5-001, Kane County

Solar + storage project NC5-001, Kane County is a 480 MW solar + storage request in interconnection study in the West interconnection queue, in Kane County, Utah, connecting to Navajo-Crystal.

Queue statusIn planning
  1. PlanningQueued May 2015 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
NC5-001
Grid region
West (non-ISO utilities)
Utility / transmission owner
Navajo-Crystal
Connection point (POI)
Navajo-Crystal 525 kV Line
Location
Kane County, Utah
Technology
Solar: 480 MW · Battery
Total requested
480 MW
Service type
NRIS and ERIS
Queue status
Active
Entered queue
11 May 2015
Proposed online date
October 2028

Location

Marker shows the centre of Kane County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Kane County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem