πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

SOLAR Β· WEST

Solar project 854, Kane County

Solar project 854, Kane County is a 190 MW solar request withdrawn in the West interconnection queue, in Kane County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2017 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
854
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Sigurd-Glen Canyon transmission line
Location
Kane County, Utah
Technology
Solar: 190 MW
Total requested
190 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN - LACK OF READINESS
Queue status
Withdrawn
Entered queue
14 March 2017
Proposed online date
December 2020

Location

Marker shows the centre of Kane County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Kane County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem