Solar project 710, Kane County

Solar project 710, Kane County is a 204 MW solar request withdrawn in the West interconnection queue, in Kane County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2015 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
710
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Sigurd-Glen Canyon
Location
Kane County, Utah
Technology
Solar: 204 MW
Total requested
204 MW
Service type
NRIS and ERIS
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
17 September 2015
Proposed online date
December 2019

Location

Marker shows the centre of Kane County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in Kane County