🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in the USA — page 12

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown9,1872,001.0 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

9,187 requests · page 12 of 184
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 361, Wheatland County
Onshore wind
600 MWIn study Wheatland, MTWest Mar 2019target 2021
Solar + storage project 25-00416, Humboldt County
Solar + storage
600 MWIn study Humboldt, NVWest Jul 2025target 2028
Other project G0768, Gilliam County
Other
600 MWIn study Gilliam, ORWest Aug 2022target 2027
Wind + storage project Company LV, White Pine County
Wind + storage
600 MWPaused / redesign White Pine, NVWest Sep 2021target 2025
Solar + storage project Q49, Millard County
Solar + storage · Intermountain Power Agency
600 MWIn study Millard, UTWest Aug 2015target 2020
Solar + storage project Company NC, Washoe County
Solar + storage
600 MWPaused / redesign Washoe, NVWest Mar 2022target 2030
Solar + storage project G0840, Douglas County
Solar + storage
600 MWIn study Douglas, WAWest Feb 2023target 2027
Geothermal project 25-00406, Churchill County
Geothermal
600 MWIn study Churchill, NVWest Jul 2025target 2029
Solar + storage project G0841, Lake County
Solar + storage
600 MWIn study Lake, ORWest Feb 2023target 2028
Gas project 25-00422, Lincoln County
Gas
600 MWIn study Lincoln, NVWest Jul 2025target 2028
Solar + storage project Company 224, Clark County
Solar + storage
600 MWPaused / redesign Clark, NVWest Aug 2022target 2030
Geothermal project 25-00409, Churchill County
Geothermal
600 MWIn study Churchill, NVWest Jul 2025target 2033
Battery storage project G0808, Douglas County
Battery storage
600 MWIn study Douglas, ORWest Sep 2022target 2030
Solar project G0673, Crook County
Solar
600 MWIn study Crook, ORWest Mar 2021target 2028
Battery storage project G0643, Crook County
Battery storage
600 MWIn study Crook, ORWest Feb 2020target 2024
Gas project T2-017, Converse County
Gas · PacifiCorp
600 MWIn study Converse, WYWest Aug 2025target 2029
Capoterra
Solar
598 MWPaused / redesign Milam, TXERCOT Jun 2022
Soleil Cantil
Solar + storage
597 MWIn study Kern, CACAISO Apr 2021target 2033
Brittlebush BESS
Battery storage
597 MWPaused / redesign Henderson, TXERCOT Jun 2022
Gas project GEN-2024-GR5, Chouteau County
Gas
594 MWAgreement signed Chouteau, OKSPP Aug 2024target 2026
Brittlebush Solar
Solar
594 MWPaused / redesign Henderson, TXERCOT Jun 2022
Gas project 401, Humphreys County
Gas
593 MWAgreement signed Humphreys, TNSoutheast Sep 2019target 2023
Solar + storage project Q80, Kern County
Solar + storage
590 MWIn study Kern, CAWest Apr 2021target 2024
Solar + storage project Q387, Navajo County
Solar + storage
588 MWIn study Navajo, AZWest Mar 2021target 2025
Jenna Eco-Electric Solar
Solar · Clean Energy Holdings, LLC
576 MWIn study Fisher, TXERCOT May 2024target 2028
Twin Palms Solar
Solar + storage
576 MWAgreement signed Riverside, CACAISO Apr 2021target 2030
Sienna 3
Solar + storage
576 MWIn study San Bernardino, CACAISO Apr 2023target 2031
Gas project 137, Pasco County
Gas · Seminole Electric Cooperative, Inc.
575 MWUnder construction Pasco, FLSoutheast Nov 2015target 2020
Sullivan Generating Station 1
Gas
575 MWAgreement signed Sullivan, INPJM Oct 2015target 2027
Sullivan Generating Station 2
Gas
575 MWAgreement signed Sullivan, INPJM Oct 2015target 2027
Solar + storage project Q53, Millard County
Solar + storage · Intermountain Power Agency
570 MWIn study Millard, UTWest Jul 2016target 2019
Gas project 25-00430, Storey County
Gas
570 MWIn study Storey, NVWest Jul 2025target 2030
RAYBURN ENERGY STATION II Gas (TEF-Due Diligence)
Gas · Rayburn Energy Station LLC
570 MWIn study Grayson, TXERCOT Jan 2025target 2028
Chesterfield CT Units 3&4
Gas
569 MWAgreement signed Chesterfield, VAPJM Sep 2019target 2029
Chesterfield CT Units 1 and 2
Gas · Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
569 MWIn study Chesterfield, VAPJM Sep 2019target 2029
Solar + storage project Q2406, Maricopa County
Solar + storage
565 MWIn study Maricopa, AZWest Feb 2024target 2029
Soledad Solar
Solar
562 MWIn study Kern, CACAISO Apr 2023target 2028
Gas project J732, Douglas County
Gas
562 MWUnder construction Douglas, WIMISO Jun 2017target 2023
Sanborn 5 Hybrid
Solar
560 MWAgreement signed Kern, CACAISO Apr 2020target 2027
Other project 110, Garfield County
Other
560 MWIn study Garfield, WAWest Jan 2021target 2025
Solar + storage project G0826, Klamath County
Solar + storage
560 MWIn study Klamath, ORWest Nov 2022target 2027
Solar + storage project J3075, Sullivan County
Solar + storage
560 MWIn study Sullivan, INMISO Sep 2022target 2025
Domestic Chicken
Solar
559 MWIn study Maricopa, AZCAISO Apr 2023target 2029
East Wonder
Solar + storage
556 MWIn study Kern, CACAISO Apr 2023target 2029
Rosamond West Solar
Solar + storage
555 MWAgreement signed Kern, CACAISO Jul 2009target 2029
Bull Creek (Osceola Generating Station)
Gas
555 MWAgreement signed Osceola, FLSoutheast Sep 2021target 2025
Big Rooter East Solar
Solar + storage · Big Rooter East, LLC
555 MWAgreement signed Robertson, TXERCOT Mar 2024target 2029
Rio Vista Solar
Solar + storage · Rio Vista Solar, LLC
554 MWIn study Pecos, TXERCOT Jun 2025target 2028
Onshore wind project 5RSC-2024-29, Yuma County
Onshore wind
554 MWIn study Yuma, COWest Jan 2024target 2027
Solar project J2478, Craighead County
Solar
550 MWIn study Craighead, ARMISO Sep 2022target 2026
Page 12 of 184

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)